30/04/2026
Project Status Updates
Project Status Update – April 2026
Since our last update in March 2026, we have continued to progress planning for the Cardinia Creek South Part 2 PSP.
Public consultation on the draft amendment (C306case) was conducted from 6 March to 12 April 2026. In total, 13 submissions were received and we continue to engage with key agencies and landowners.
We are currently working to review and resolve all submissions. As part of this process, the amendment documents will be updated as required.
In the coming months, along with reviewing submissions, we will be preparing the Infrastructure Contributions Plan (ICP) as part of the draft amendment package for Ministerial approval.