The Victorian Planning Authority (VPA) has been progressing the planning for Wonthaggi North East by completing technical work to finalise the recommendations of the VPA Projects Standing Advisory Committee (SAC).
In August 2022, the VPA SAC released its report into our plans for Wonthaggi North East, which recommended updates and additional information regarding drainage and development infrastructure costings.
Since our last update in May, we have continued to work with technical experts to finalise the Wonthaggi North East Revised Drainage Strategy and Wonthaggi North East Functional Designs and Costings Report in July 2023.
In the coming weeks we will be focused on finalising the planning scheme amendment and associated documents to submit to the Minister for Planning for consideration.