Wonthaggi North East PSP

Amendment C152 to the Bass Coast Planning Scheme

The Wonthaggi North East Precinct Structure Plan (PSP) and Wonthaggi North East Development Contributions Plan (DCP) were approved by the Minister for Planning and gazetted on 18 January 2024 under Amendment C152 to the Bass Coast Planning Scheme.

To view a copy of the final amendment documentation, including the Wonthaggi North East Precinct Structure Plan, refer to:

Update on the Wonthaggi North East Environmental Audit Overlay – 21 June 2024

On 21 June 2024, Amendment C167basc was gazetted, which removed the Environmental Audit Overlay (EAO) from 115 lots where a preliminary risk screen assessment (PRSA) has determined that the land is unlikely to be contaminated and does not require an environmental audit. The Amendment was requested by Bass Coast Shire Council following three private developers commissioning their own PRSAs.  Details of the amendment can be viewed at https://planning-schemes.app.planning.vic.gov.au/All%20schemes/amendments/C167basc?schemeCode=basc

The PRSA process is ongoing in the remainder Wonthaggi North East Precinct.

Previous Project Status Updates

Supporting Documentation

Wonthaggi North East Precinct Structure Plan (Approved and Gazetted)
Wonthaggi North East Precinct Structure Plan (Approved and Gazetted) PDF  Version
Wonthaggi North East Native Vegetation Precinct Plan (Approved and Gazetted)
Wonthaggi North East Native Vegetation Precinct Plan (Approved and Gazetted) PDF  Version
Wonthaggi North East Development Contributions Plan (Approved and Gazetted) Part 1
Wonthaggi North East Development Contributions Plan (Approved and Gazetted) Part 1 PDF  Version
Wonthaggi North East Development Contributions Plan (Approved and Gazetted) Part 2
Wonthaggi North East Development Contributions Plan (Approved and Gazetted) Part 2 PDF  Version
Wonthaggi North East Development Contributions Plan (Approved and Gazetted) Part 3
Wonthaggi North East Development Contributions Plan (Approved and Gazetted) Part 3 PDF  Version
Wonthaggi North East - IN 09 Concept Design (Stantec) 2022
Wonthaggi North East - IN 09 Concept Design (Stantec) 2022 PDF  Version
Wonthaggi North East - IN 04 Concept Design (Stantec) 2022
Wonthaggi North East - IN 04 Concept Design (Stantec) 2022 PDF  Version
Wonthaggi North East - IN-04 Broad Level Cost Estimate (Stantec) 2022
Wonthaggi North East - IN-04 Broad Level Cost Estimate (Stantec) 2022 PDF  Version
Wonthaggi North East - IN-09 Broad Level Cost Estimate (Stantec) 2022
Wonthaggi North East - IN-09 Broad Level Cost Estimate (Stantec) 2022 PDF  Version
Wonthaggi North East - Public consultation report - December 2020
Wonthaggi North East - Public consultation report - December 2020 PDF  Version
VPA Projects Standing Advisory Committee Final Report - Draft Bass Coast Planning Scheme Amendment C152basc - Referral 3 - Wonthaggi North East PSP - August 2022
VPA Projects Standing Advisory Committee Final Report - Draft Bass Coast Planning Scheme Amendment C152basc - Referral 3 - Wonthaggi North East PSP - August 2022 PDF  Version
Wonthaggi North East PSP - VPASAC - Referral 3 - Letter to all parties following Tranche 1 (Planning Panels Victoria) April 2021
Wonthaggi North East PSP - VPASAC - Referral 3 - Letter to all parties following Tranche 1 (Planning Panels Victoria) April 2021 PDF  Version
Wonthaggi North East Precinct - Referral Letter - February 2021
Wonthaggi North East Precinct - Referral Letter - February 2021 PDF  Version
Wonthaggi North East PSP - Storm Water Management Infrastructure - Functional Design CAD v5a - August 2023 - Part 1
Wonthaggi North East PSP - Storm Water Management Infrastructure - Functional Design CAD v5a - August 2023 - Part 1 PDF  Version
Wonthaggi North East PSP - Storm Water Management Infrastructure - Functional Design CAD v5a - August 2023 - Part 2
Wonthaggi North East PSP - Storm Water Management Infrastructure - Functional Design CAD v5a - August 2023 - Part 2 PDF  Version
Wonthaggi North East PSP - Storm Water Management Infrastructure - Functional Design CAD v5a - August 2023 - Part 3
Wonthaggi North East PSP - Storm Water Management Infrastructure - Functional Design CAD v5a - August 2023 - Part 3 PDF  Version
Wonthaggi North East PSP - Storm Water Management Infrastructure - Functional Design CAD v5a - August 2023 - Part 4
Wonthaggi North East PSP - Storm Water Management Infrastructure - Functional Design CAD v5a - August 2023 - Part 4 PDF  Version