Project Status Update – December 2025
Due to scheduling constraints outside the VPA’s control, the Standing Advisory Committee (SAC) hearing that was scheduled to commence in October could not conclude as planned. As a result, the hearing has been split into two tranches. Tranche 1 was held over four days between 15 October 2025 and 25 October 2025 and Tranche 2 has been rescheduled for February 2026, with exact dates to be confirmed.
Since our last update in September, we have:
- Circulated all amendment documents, including the Precinct Structure Plan, background report, plan sets and planning ordinance, for consideration at the SAC hearing.
- Participated in Tranche 1 of the SAC hearing, which focused on key strategic, land-use, transport and infrastructure matters.
- Collaborated with submitters, agencies and landowners to clarify issues raised during Tranche 1 and identify pathways toward resolution.
- Commenced preparatory work for drainage and development contributions matters, which will be addressed in Tranche 2.
Between now and SAC Tranche 2 hearing, the project team will:
- Continue engaging with submitters and stakeholders to resolve outstanding issues wherever possible.
- Prepare updated technical material where required to support issue resolution and the February 2026 hearing.
- Work with agencies to refine inputs to the Drainage Services Scheme and Infrastructure Contributions Plan, given their importance to Tranche 2.
Previous Project Status Updates
- Project Status Update – September 2025
- Project Status Update – July 2025
- Project Status Update – June 2025
- Project Status Update – March 2025
- Project Status Update – January 2025
- Project Status Update – November 2024
- Project Status Update – September 2024
- Project Status Update – July 2024
- Project Status Update – May 2024
- Project Status Update – March 2024
- Project Status Update – November 2023
- Project Status Update – July 2023
- Project Status Update – April 2023
- Project Status Update – February 2023
- Project Status Update – November 2022
- Project Status Update – October 2022
- Devon Meadows and Casey Fields South PSP & ICP – Stakeholder Update – June 2022 (PDF)