Project Status Update – July 2024
We have been working with the City of Greater Geelong to progress planning for the precinct.
Since our last update in May 2024, we have:
- Begun drafting a Precinct Structure Plan for council and state agency consultation.
- Progressed the drainage and flooding, sodic soils, post-contact heritage, aboriginal cultural values, biodiversity, landscape and visual impact and high level servicing assessments.
- Sought feedback from council and the Department of Transport and Planning on the scope for an integrated transport modelling assessment.
In the coming months, we will be focused on progressing technical work and preparing a draft amendment package in preparation for council and state agency consultation in the third quarter of 2024.