Project Status Updates
Project Status Updates – September 2024
We have been working with Golden Plains Shire Council and other key stakeholders to progress planning for the Bannockburn South East precinct to prepare for Public Exhibition of the Precinct Structure Plan (PSP) package in early 2025.
Since our last update in July 2024, we have:
- Procured key technical work to inform the exhibition of the PSP and planning scheme amendment package.
- Met with the Wadawurrung Traditional Owners Aboriginal Corporation to discuss pathways for the protection and management of cultural heritage through the PSP process.
- Continued discussions with other key stakeholders on issues surrounding drainage, transport, land contamination and adverse amenity impacts.
We have also uploaded the following reports, which are now viewable in the Background Studies tab of the webpage:
- Bannockburn South East PSP – DRAFT Sodic Soils Assessment (WSP) July 2024
- Bannockburn South East PSP – Economic & Retail Assessment – Addendum (Ethos Urban) July 2024
- Bannockburn South East PSP – Community Infrastructure Assessment (ASR Research) July 2024
- Bannockburn South East PSP – Soil Desktop Assessment – Sodic-Dispersive Soils and Contamination Risks (WSP) August 2024
In the coming months, we will be focused on preparing for public consultation through resolving outstanding matters and initiating technical work such as land valuations. We will also prepare exhibition documentation including the PSP, Development Contributions Plan and the proposed Planning Scheme Ordinance.