Project Status Updates

Project Status Updates – September 2024

We have been working with Hume City Council to progress the planning for Greenvale North Part 2 by completing a period of community consultation on the draft Precinct Structure Plan (PSP). We have also released our background report, and associated planning scheme amendment documentation. 

Since our last update in July 2024, we have: 

  • Begun to review and sort submissions received during community consultation. 
  • Continued to investigate alignment and resolution on submissions.  

In the coming months, we will be focused on resolving submissions that were received during the consultation period. We will also prepare a report detailing the community engagement that has been undertaken. If issues cannot be resolved, we will prepare for the VPA Projects Standing Advisory Committee, who will hear the details and advise on unresolved matters.

Previous Project Status Updates