Project Status Updates

Project Status Update – June 2026

Since our last update in April 2026, we have received the Standing Advisory Committee’s (SAC) Report for the Ballarat North Precinct Structure Plan (PSP) and Development Contributions Plan (DCP).

The SAC is an independent panel appointed to provide recommendations to the project team on how to address key issues.

The SAC have provided advice relating to:

  • Development Contributions Plan (specific items and costings).
  • Transport Network (specified network components).
  • Drainage Infrastructure (location and sizing of assets).
  • Southeast P–6 Government School site (strategic justification).

We have commenced revising the draft planning scheme ordinances, planning scheme maps, PSP and DCP documents to incorporate changes arising from recommendations of the SAC Report.

In the coming months, we will focus on finalising the PSP and DCP for lodgement with the Minister for Planning for consideration.