Project Status Updates

Project Status Updates – November 2023

We have been working with Hume City Council to progress the planning for Greenvale North (Part 2) by finalising background technical reports and commencing drafting of the Precinct Structure Plan.  

Since our last update in July, we have:   

  • Discussed the project with residents of Greenvale at community information sessions.   
  • Finalised the background technical reports to inform our plans.  
  • Commenced preparation of the PSP, place-based plan and planning scheme ordinance. 
  • Commenced preparation of the draft amendment package for agency validation. 

On 20 September, the Victorian Government released Victoria’s Housing Statement: The decade ahead 2024-2034, in which it announced the Victorian Planning Authority will continue preparing Precinct Structure Plans (PSPs) for new housing and jobs in Melbourne and regional Victoria. We will conduct further work across 21 projects to deliver more than 60,000 homes and 60,000 jobs. These projects will deliver a sustainable supply of greenfield land, and more jobs close to home.  

Greenvale North (Part 2) PSP is one of the 21 projects named in the Housing Statement. 

In the coming months we will be focused on completing agency validation of the draft amendment documents in preparation for public exhibition in early 2024.  

We are now in the process of updating our work program and confirming new timings for this project. We will provide another update with more details on our next steps once our work program is confirmed.  

Previous Project Status Updates