22/03/2024
Project Status Updates
Project Status Updates – March 2024
We are continuing to collaborate with the City of Casey to progress feedback from key stakeholders, such as other government departments, to inform the Casey Fields South and Devon Meadows precinct structure plan (PSP) and infrastructure contributions plan (ICP).
Since our last update in November 2023, we have:
- Continued to work with Melbourne Water on the requirements for the drainage services scheme (DSS) and the Department of Education (DET) to understand implications for the precincts.
- Begun work on the strategic transport plan and integrated transport assessment.
In the coming months, we will focus on updating our place-based plan based on agency feedback and amendments so that we can seek authorisation from the Minister for Planning to undertake a public exhibition in the second half of 2024.
Previous Project Status Updates
- Project Status Updates – November 2023
- Project Status Updates – July 2023
- Project Status Updates – April 2023
- Project Status Updates – February 2023
- Project Status Updates – November 2022
- Project Status Updates – October 2022
- Devon Meadows and Casey Fields South PSP & ICP – Stakeholder Update – June 2022 (PDF)