Project Status Updates

Project Status Updates – July 2024

We have been working with the City of Casey to progress the planning for the Croskell (Employment) project.   

Since our last update in May 2024, we have:  

  • Finalised the draft Precinct Structure Plan (PSP) and planning scheme amendment package in preparation for public consultation. 
  • Determined that a supplementary levy will be required which means that a draft Infrastructure Contributions Plan will be made available as part of public consultation. 
  • Worked with Melbourne Water to progress the precinct’s drainage strategy. Find out more about the Croskell (Employment) PSP draft drainage strategy here: https://letstalk.melbournewater.com.au/croskell-psp-draft-drainage-strategy 
  • Published the Cultural Heritage Interpretation Strategy.  
  • Several other background reports – notably the Integrated Transport Assessment and updates to the Economics Report, Post-Contact Heritage Report and others – are nearing completion and will be published online upon commencement of public consultation.  

In the coming weeks we will be preparing to release our draft plans for Croskell (Employment) for public consultation. We are not currently able to confirm a commencement date for public consultation, but will advise subscribers via email when we can. 

Previous Project Status Updates