Project Status Updates – October 2025

East of Aberline Consultation Update & Drainage Technical Report Revision

The VPA has prepared a draft amendment (C217warr) to the Warrnambool Planning Scheme to implement the East of Aberline Precinct Structure Plan (PSP) and Development Contributions Plan (DCP), guiding future development in the area. Public consultation is currently open and will close on 20 October 2025.

For more information on session dates, times, locations and to register your attendance to these sessions, please visit Engage Victoria via https://engage.vic.gov.au/EastOfAberline 

Updated Drainage Technical Report

The VPA has released an updated Drainage Technical Report on our Engage Victoria and project webpage.  

Key changes include: 

  • Replacement of the previous Drainage Proof of Concept with Drainage Functional Designs and costings. 
  • Revised drainage solutions, where possible, to optimise land take. 
  • Updated costings to reflect Functional Designs. 

We’re encouraging anyone preparing a submission on drainage outcomes to review this technical work when finalising their submissions.  

This work will be further refined in response to submissions and incorporated into the final amendment package. If you are a submitter on this matter, you will be updated in due course. 