April 28, 2023
Project Status Updates
Project Status Updates – April 2023
The Victorian Planning Authority (VPA) has been working with Mitchell Shire Council to progress the planning for Wallan South by finalising technical studies and responding to feedback we’ve received from government agencies.
We are finalising the draft Wallan South Precinct Structure Plan (PSP) and Supplementary Levy Infrastructure Contributions Plan (ICP) for public consultation. We also continue to progress Drainage Services Scheme (DSS) options with Mitchell Shire Council and Melbourne Water.
Since our last update in March 2023, we have:
- Finalised and published the transport report available under the Background Studies tab
- Commenced a social and affordable housing study
- Received draft concept drawings and costings for the ICP.
In the coming months we will finalise the amendment package to prepare for public consultation to take place, pending Ministerial approval of the Beveridge North West PSP.